Stadiu Lucrari August


  • Stadiu Lucrari August
  • Stadiu Lucrari August
  • Stadiu Lucrari August
  • Stadiu Lucrari August
  • Stadiu Lucrari August
  • Stadiu Lucrari August
  • Stadiu Lucrari August
  • Stadiu Lucrari August

Corp 2

Fatade:
Fatada Vest – Inceput lucrari montaj balustrade metalice + turnari sape balcoane
Fatada Nord – Finalizare termosistem
Fatada Sud – Finalizare termosistem – sc. 1
Fatada Est – Finalizare termosistem sc. 2; Inceput termosistem sc. 3

Instalatii:
Finalizat instalatii sanitare si electrice in apartamente
Finalizat instalatii incalzire in pardoseala
Instalatii electrice – Tablouri electrice case de scara

Finisaj:
Finalizat Tencuieli
Finalizat Glet – etaj 5 si 6
Finalizat Sape
Placare cu gresie pe Casa Scarii 1, 3 si 5

Finalizat structura beton armat:
Zona accese principale si secundare

Corp 1B

Fatada:
Finalizat tamplarie apartamente–Rest de montat sticla et. 5 + 6Montaj tamplarie spatiu comercial – 90% finalizata
Fatada Est – Termosistem (decorativa) 90%
Montaj glafuri tabla peste atice terasa
Montaj structura pereti corina parter si etaj 1

Finisaje:
Finalizat placare cu vata – subsol
Inceput lucrari tencuieli sc. 1 + sc 2 – etaj tehnic

Instalatii:
Se executa instalatii sanitare Etaj 3-> 6
Se executa instalatii electrice Etaj 6 -> 6

Corp 1A

Structura:
Lucrari de zidarie